Shipbuilding Payment Milestones, Costs and Escrow Protection
Structure shipyard costs and payment milestones so a build won’t stall: physical milestones, escrow, refund guarantee, price adjustment. USD contracts.
- USD
- All contract values
- 4
- Clauses that most often save a project
- 5
- Things to look for in every quotation
Short answer
Most failed vessel projects in Indonesia fail not on the technical side but in their payment structure. This page explains how Kendari Shipyard sets up costs, shipbuilding payment milestones, escrow and adjustment clauses so that the risk of a stalled project is reduced from the moment the contract is signed.
Root cause
The real source of stalled projects
When a build stops, the usual explanation is that the shipyard was incompetent. In reality, almost every case we handle has the same root: money flows faster than the work. Calendar-based payment milestones quietly create that gap. By the fourth month, the owner has paid four milestones while physical progress equals only two. Those two extra milestones are hidden debt, and once the shipyard runs out of working capital, there is no longer any commercial reason to continue.
That is why the most decisive fix is not adding more supervision, but changing what payment is based on.
Milestones
Payment milestones tied to physical progress
| Milestone | Evidence for releasing funds | Verified by |
|---|---|---|
| Drawings approved | Drawing set bearing approval stamps | Owner + classification society |
| Materials delivered | On-site materials list, dated photos | Build supervision |
| Keel laying | Signed keel-laying record | Owner + surveyor |
| Hull watertight | Watertightness test results | Surveyor |
| Engine installed | Turning test, shaft alignment | Build supervision |
| Sea trial | Sea trial report | Owner + surveyor |
| Handover | Defect list closed out, documents complete | Owner |
The rule we hold to is simple: if a milestone cannot be photographed, measured and signed off, it is not a milestone. The technical stages behind it are set out on the new vessel construction page.
Protection
Escrow and retention
Escrow places milestone funds with a third party that releases them only after the milestone is verified. The benefit runs both ways, and that is what is often missed: the owner is protected from paying for work that does not yet exist, while the shipyard gains certainty that the funds for the next stage are genuinely available and will not disappear midway.
Retention complements it. Part of the contract value is held back until the warranty period has passed, so defects that appear only after the vessel enters service still have funds for rectification. Without retention, the defect list after handover tends to become an endless argument.
Cost drivers
What drives cost
In a newbuild, the three biggest variables are hull material, the propulsion system and the level of interior finish. The one owners most often underestimate is the last: outfitting and accommodation work absorbs a far larger share of the budget than first imagined, because that is where the largest number of items sits. On stalled vessel completion projects, the breakdown is different again — the biggest costs are often in dismantling, inspecting and correcting old work before a single piece of new work begins.
For operating vessels, the expense that must be budgeted routinely is the dry docking cycle. We set out the framework in the article on annual dry docking costs, and its application to workboat fleets on the tugboat and barge page.
Quotations
Reading a shipyard quotation critically
A quotation that looks cheap and a quotation that is genuinely cheap are two different things, and the difference almost always lies in what is not stated. Here are five things an owner should look for in every quotation.
Whether the scope is written item by item with quantities, or only as a lump sum. Whether preparatory work — dismantling, cleaning, inspection — appears as its own line item or is hidden. Whether there is a clear boundary between what is included and what is not, for example whether the interior, marine electrical work and certification are covered. Whether there is a written variation order (VO) mechanism. And whether there are hidden assumptions, for example that certain materials will be supplied by the owner.
A quotation that does not answer all five is not a cheaper quotation but an incomplete one. The difference will surface later as additional invoices, at a point when the owner has already lost bargaining power because the vessel is sitting at the shipyard.
Contingency
How we treat contingency and findings
Any work that touches an old structure will inevitably turn up findings that cannot be known before it is opened. There are two ways to handle this, and only one is honest. The first is to hide that risk inside an inflated fixed price, so the owner pays for possibilities that may never happen. The second is to state the contingency openly as a separate line item, with the rule that it is used only if findings actually appear and are approved in writing.
We use the second approach. As a result, our initial figure sometimes looks higher than quotations that bury the risk in a single lump sum. The difference is that the owner knows exactly what they are paying for, and unused contingency does not pass to us. The cost framework for stalled vessels is set out in the article on the cost of completing a stalled vessel.
Contract clauses
Clauses that should be in the contract
Four clauses most often save a project: material price adjustment with an agreed reference and threshold; a written variation order procedure, complete with cost and time consequences; the owner’s right to stop payment if a milestone fails verification; and terms on ownership of materials that have been paid for but not yet installed. That last clause is the one most fought over when a project actually stops.
See also: About Kendari Shipyard
FAQ
Frequently asked questions
Why are date-based payment milestones dangerous?
Because payment becomes detached from physical progress. When the shipyard has been paid faster than the work it has produced, the incentive to finish the project weakens, and the gap grows unseen until the project stops.
What is a refund guarantee and when should you ask for one?
A refund guarantee is a guarantee that the down payment will be returned if the shipyard fails to meet its obligations. It is most relevant on high-value newbuild projects with a significant down payment at the start of the contract.
How does escrow protect both parties?
Funds are placed with a third party and released only after a milestone is verified. The owner is protected from paying for work that does not yet exist, while the shipyard gains certainty that the funds are genuinely available.
How should material price increases mid-project be handled?
With an adjustment clause agreed at the outset that specifies the price reference and the change threshold. A fixed-price contract without this clause actually increases the risk of the project stopping when the market moves.
In what currency are contract values stated?
All quotations, payment milestones and contract values are stated in USD. This single basis removes exchange-rate disputes mid-project and gives one consistent way to compare quotations between shipyards.